Actividad de Energy Syneox

Activity

Substations

Electrical Traction substations for line 2C of the Santo Domingo Metro. Electrification.

Client

Office for the Reorganization of Transport (OPRET)

Location

Dominican Republic

Typology

Metro


Key Points:

  • Two-ring feeding between TS Los Alcarrizos and TPSS Los Alcarrizos
  • Interconnections between traction substations
    • TPSS María Montez – TPSS los Alcarrizos
    • TPSS María Montez – TPSS Manoguayabo
    • TPSS Manoguayabo – TPSS 27 de Ferbrero
    • TPSS 27 de Febrero – TPSS Los Alcarrizos
  • Adaptation of TPSS María de Montez AC distribution
  • 3 new traction substations TPSS
    • TPSS Manoguaybo
    • TPSS 27 de Febrero
    • TPSS Los Alcarrizos

The new L2C section

The new L2C section has the following characteristics:

  • 7.33 km length
  • 5 new stations starting from the turnback siding in María Montez
    • Manoguayabo
    • Monumental
    • 27 de Febrero
    • Pantoja
    • Los Alcarrizos

  • New 8-track depot in Luperón of 120 m in length with its corresponding marshalling yard, between the María Montez and Pedro Francisco Bono stations. Currently under construction

The line runs under the Enriquillo neighborhood to the vicinity of kilometer 9.5 of the Juan Pablo Duarte Highway, through a section of tunnel about 891.5 meters long, to, after a transition of about 120 meters of cut-and-cover tunnel, continue on a viaduct parallel to the aforementioned highway until its intersection with Duarte Street in the Los Alcarrizos Sector.  where the last of the five new stations will be located, which will have a turnback siding of about 509 meters.

At the last station it has a connection with the cable car.